Supra Énergie projects

Projects

From network maintenance to electrical substation commissioning, explore six projects completed by our teams.

Open a project to explore its scope and challenges.

01 — Projects

Renewable energy

Appareillage extérieur du poste électrique du parc éolien Seigneurie de Beaupré

MAINTENANCE

Seigneurie de Beaupré wind farm

Boralex
Beaupré · 2020

Explore the project

The project

At the Seigneurie de Beaupré wind farm, Supra Énergie carried out annual testing of the electrical substation and replaced 35 kV cable splices, scheduling the work around wind conditions to limit the impact of production interruptions.

Our scope of work

As part of the annual maintenance of the 315/35 kV high-voltage substation, Supra Énergie was tasked with testing the existing outdoor equipment. The work also included replacing 35 kV splices on the wind farm’s collector network.

Equipment involved

  • 315 kV power transformer
  • Grounding transformer
  • 35 kV circuit breaker
  • Disconnect switch
  • Voltage and current transformers (VTs and CTs)

The challenge

The wind farm's output depends directly on the wind. The work date and sequence were therefore adapted to wind conditions to limit the outage's impact on energy production.

Supra Énergie’s contribution

  • An experienced team
  • Knowledge of the facility
  • Fast, advanced test equipment
Éolienne du parc Lanfine au coucher du soleil

CONSTRUCTION AND COMMISSIONING

Lanfine wind farm

Borea
Lanfine · 2022

Explore the project

Our scope of work

Construction and commissioning of the wind farm.

02 — Projects

Industrial

Transformateur de puissance et appareillage extérieur au poste électrique Alcoa Deschambault

COMMISSIONING

Alcoa Deschambault electrical substation

Alcoa
Deschambault · 2021

Explore the project

The project

Alcoa increased the capacity of its existing electrical substation by 500 MW. The project included the addition of a 480 MVA, 315 kV transformer, circuit breakers and disconnect switches, as well as a new control building with protection relays.

Our scope of work

Test and commission the new equipment, verify the control and automation systems, then commission the substation at the end of construction.

Equipment involved

  • 315 kV power transformer
  • 315 and 69 kV circuit breakers
  • Disconnect switches
  • VTs and CTs
  • Protection relays

The challenge

Procurement delays cut the planned testing period in half, with no extension to the deadline. Additional team members and evening and weekend work enabled the project to be delivered on time.

Supra Énergie’s contribution

  • Experienced team
  • Turnkey service
  • Knowledge of the facility
  • Flexibility
Équipements extérieurs du SVC installé au poste électrique de l’usine Finkl Steel

COMMISSIONING

Finkl Steel plant

GE Power Conversion
Sorel · 2020–2021

Explore the project

The project

For GE Power Conversion, Supra Énergie tested an SVC at the Finkl Steel plant, then supported assembly quality assurance and stakeholder coordination through to final commissioning of the installation.

Our scope of work

The installation of a GE France SVC was intended to improve the plant’s power factor by replacing the existing passive capacitor bank. Supra Énergie was responsible for testing the outdoor equipment, thyristors and control panel. The scope also expanded to include installation quality assurance and coordination of the parties involved through final commissioning.

Equipment involved

  • 45 kV circuit breaker
  • Reactor
  • Capacitor bank
  • Disconnect switch
  • Voltage and current transformers (VTs and CTs)
  • Thyristors
  • Protection relays
  • Cooling unit
  • Control panel

The challenge

Because this type of installation is uncommon in Quebec, the team provided installation support beyond the planned testing. With project management conducted remotely due to COVID-19, Supra Énergie coordinated the mechanical, civil engineering and electrical teams through to commissioning.

Supra Énergie’s contribution

  • Experience with multiple SVC projects
  • Fast, advanced test equipment
  • The ability to adapt as the scope evolves

03 — Projects

Public utilities

Vue du poste électrique Jean-Dechêne de la Ville de Saguenay

COMMISSIONING

Jean-Dechêne electrical substation

Ville de Saguenay
Saguenay · 2020

Explore the project

The project

The City of Saguenay doubled the capacity of the Jean-Dechêne substation by adding two 47 MVA, 161 kV transformers and eight 25 kV outgoing feeders. The project also included complete replacement of the SCADA system and protection relays.

Our scope of work

Test the existing and newly installed equipment, verify the control and automation systems, then commission the substation at the end of the work.

Equipment involved

  • Power transformers
  • 161 and 25 kV circuit breakers
  • Disconnect switches
  • VTs and CTs
  • Protection relays

The challenge

Procurement delays cut the planned testing period in half, with no extension to the deadline. Additional team members and evening and weekend work enabled the project to be delivered on time.

Supra Énergie’s contribution

  • Experienced team
  • Turnkey service
  • Knowledge of the facility
  • Flexibility
Vue aérienne des installations et des quais du Port de Québec

MAINTENANCE

Port de Québec

Port de Québec
Québec · 2021–2025

Explore the project

The project

At the Port de Québec, Supra Énergie provided preventive maintenance for the 25 kV network and emergency support during outages under a five-year contract tailored to the constraints of day-to-day port operations.

Our scope of work

Supra Énergie’s five-year contract covered preventive maintenance of the existing substations and their switchgear. It also included repairs, oil sampling and treatment, and emergency service in the event of an outage or equipment failure.

Equipment involved

  • Power transformers
  • Circuit breakers
  • Disconnect switches
  • Voltage and current transformers (VTs and CTs)

The challenge

The electrical network serves ships, terminals and industrial facilities. Work had to be organized at short notice to meet port operational needs and limit the impact of power outages.

Supra Énergie’s contribution

  • An experienced team
  • Knowledge of the facility
  • Fast, advanced test equipment

Let’s talk about your next project.